  • Question 251:

    Which describes risk impact?

    A. Timeframe within which the risk might occur

    B. The trigger that occurred giving rise to the risk

    C. The effect of the risk on the delivery of project objectives

    D. How likely the risk is to occur in a given project situation

  • Question 252:

    Which is a purpose of a Project Brief?

    A. Capture lessons from previous projects

    B. Ensure that there is a common understanding of the starting point for the project

    C. Confirm that the Project Plan is able to deliver the Business Case

    D. Define the quality techniques and standards to be applied during the project

  • Question 253:

    Which is a purpose of the Business Case theme?

    A. Identify which role is responsible for producing the Business Case

    B. Identify the project's outputs

    C. Establish the controls to manage changes that may impact the project benefits

    D. Establish a viable investment proposition

  • Question 254:

    Who is the key project decision-maker in the project management team?

    A. Corporate management

    B. Executive

    C. Change Authority

    D. Project Manager

  • Question 255:

    Which is a purpose of a Product Description?

    A. Provide the cost tolerance available for individual products

    B. Define reporting frequency

    C. Record the quality checks completed for the End Stage Report

    D. Document the level of quality required of a product

  • Question 256:

    Which is a purpose of a Project Product Description?

    A. Records the costs and timescales for delivery of the project's final product

    B. Shows the dependencies between the project's products to aid planning

    C. Provides a list of all the products to be delivered by the project

    D. Defines what the project must deliver in order to gain acceptance

  • Question 257:

    Which product identifies the management stages and timescales of a project?

    A. Project Brief

    B. Project Product Description

    C. Project Plan

    D. Initiation Stage Plan

  • Question 258:

    How should the Team Manager report that tolerances are forecast to be exceeded?

    A. Create an Exception Report

    B. Create a Highlight Report

    C. Raise an issue

    D. Grant a concession

  • Question 259:

    Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.

    A. Change

    B. Plans

    C. Quality

    D. Risk

  • Question 260:

    Which is a purpose of quality planning?

    A. Define the structure of the project management team

    B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product

    C. Document approval records for those project products that have met their quality criteria

    D. Produce the Project Plan with resource and schedule information

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.