Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
A. Configuration Item Records
B. Business Case
C. Project Brief
D. project management team and/or role descriptions
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
A. Raise a request for change
B. Raise an off-specification
C. Write an Exception Report
D. Amend the Work Package
Which is NOT confirmed during the Initiating a Project process?
A. How the management and specialist products of the project should be baselined
B. How the method will be tailored for the size and complexity of the project
C. Whether the expected benefits have been achieved
D. Who will make decisions on any changes during the project
Where should the names of those who are to approve a product be recorded?
A. Product Status Account
B. Product Description
C. Configuration Item Record
D. Checkpoint Report
Which theme defines the accountability for realization of the project's benefits?
A. Plans
B. Progress
C. Organization
D. Quality
Which enables the project's products and all interdependencies to be clearly identified and documented?
A. Product breakdown structure
B. Quality Management Strategy
C. Product-based planning technique
D. Quality review technique
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.
A. any type of project
B. programmes and projects
C. all types of programmes
D. business as usual
Which is a valid statement about the Project Support role?
A. Can be performed by the Project Manager
B. Is an optional role for a PRINCE2 project
C. Produces Checkpoint Reports for the Project Manager
D. Can be combined with the Project Assurance role
Identify the missing words in the following sentence.
The Team Manager should check the [ ? ] for any interfaces that must be maintained while developing products.
A. Project Product Description
B. Project Plan
C. Checkpoint Report
D. Work Package
Which is a purpose of the Organization theme?
A. Ensure that the project organization structure will enable the project to deliver the business benefits in the required time frame
B. Define accountability within the project
C. Identify risk owners for the project
D. Define the quality methods and responsibilities for the management of the project
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.