What is used to identify any organization or interested party who needs to be informed of project closure?
A. Configuration Management Strategy
B. Project management team structure
C. Communication Management Strategy
D. Project Brief
Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?
A. Those that have been completed, but have NOT been quality checked
B. Those that have been broken down into sub-products
C. Those to be created outside the scope of the project
D. Those dependent on more than one other product
Which is NOT a PRINCE2 principle?
A. Learn from experience
B. Customer/supplier environment
C. Defined roles and responsibilities
D. Continued business justification
Which is a purpose of the Directing a Project process?
A. Provide the information required to confirm if it is worthwhile to initiate a project
B. Enable overall control of a project to be exercised by the Project Board
C. Establish the level of control required by the Project Board after initiation
D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Which is NOT a benefit of using PRINCE2?
A. Defines specific leadership, motivational skills and other interpersonal skills required
B. Can be applied to any type of project
C. Promotes learning and continuous improvement
D. Defines a thorough but economical structure of reports
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
A. Plans
B. Business Case
C. Risk
D. Quality
Which statement applies to Stage Plans?
A. Always have the same duration as the Project Plan
B. Are produced at the same time as the Project Initiation Documentation
C. Assist the Project Manager in the day-to-day running and control of the project
D. Provide a baseline against which the Project Board monitor overall progress
Which of the following are objectives of the Directing a Project process?
1.
Ensure corporate or programme management has an interface to a project
2.
Ensure that work on products allocated to a team is authorized
3.
Ensure there is authority to initiate a project
4.
Ensure that a project remains viable
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Which should be funded from a change budget?
A. The Starting up a Project process
B. A fallback plan
C. An agreed change to the scope of a project
D. A change to a plan, within allocated tolerances, due to poor estimating
Which is a true statement about acceptance criteria?
A. Acceptance criteria are used to produce the customer's quality expectations
B. Acceptance criteria are less specific and precise than customer's quality expectations
C. Once agreed, acceptance criteria CANNOT be changed
D. Acceptance criteria should be agreed between the customer and the supplier
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.