FILL BLANK Fill in the blank with an appropriate phrase. The _________ is the risk or danger of an action or an event, a method or a (technical) process that still conceives these dangers even if all theoretically possible safety measures would be applied.
FILL BLANK Fill in the blank with an appropriate phrase. ________is the study of how the variation (uncertainty) in the output of a mathematical model can be apportioned, qualitatively or quantitatively, to different sources of variation in the input of a model.
An organization is executing two projects -- Project A and Project B -- simultaneously. A previously identified risk will impact the schedule for Project A. While executing the mitigation plan, a number of residual risks are identified that could provide cost savings for Project
B.
Which action should the risk manager for Project A take?
A. Review the findings in Project A's closure documents and propose a new organizational process for portfolio risk management.A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.
Which steps should the risk manager consider when updating relevant project documents?
A. Update the issue log with relevant information as the immediate concern for key stakeholders.A project team is leading a software development project. During the project kickoff meeting, the risk manager discovers that a vendor has not finalized the timeline for delivering an essential component. This creates uncertainty in the overall project schedule.
What should the risk manager do to address the risk?
A. Hold a meeting to assess the risk's impact and create a response plan with alternative timelines.At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it's complete since it is such a short and simple project.
How should the risk manager respond to this comment?
A. The risk register must only be updated if a change is approved during the project.A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ?0% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ?% and reports on the basis of any variance outside that range.
How should the risk manager respond?
A. Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.A major data center initiative involves performing a sensitivity analysis to determine the center's required amount of disaster recovery. Several key stakeholders are in disagreement about which level of disaster recovery is required. The lessons learned disaster recovery plans, and the difference for this data center is its geographical location and unique climate requirements. The database includes examples from previous similar initiatives, as well as the competitor's advertised plans.
What should the risk manager do to quantify the risk?
A. Initiate a 360-degree assessment.The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.
What should the risk management team have done to manage this situation?
A. Ensured to include the stakeholders in the team discussionsA new project is about to start, and the risk manager wants to review some documents that could be relevant for risk identification. Which document will help the risk manager in this process?
A. Detailed work breakdown structure (WBS)Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.