  • Question 641:

    Which of the following is a means of reaching a group decision in which everyone agrees on a single course of action?

    A. Dictatorship

    B. Majority

    C. Plurality

    D. Unanimity

  • Question 642:

    Which of the following is a complete set of indexed contract documentation, including the closed contract?

    A. Procurement package

    B. Negotiated settlements

    C. Procurement file

    D. Procurement management plan

  • Question 643:

    Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?

    A. Configuration definition, configuration status accounting, configuration monitoring and control

    B. Configuration identification, configuration status accounting, configuration verification and audit

    C. Configuration identification, configuration status reporting, configuration verification and audit

    D. Configuration definition, configuration status reporting, configuration monitoring and Control

  • Question 644:

    Which of the following correctly describes when organizations and stakeholders are willing to accept varying degrees of risk?

    A. Risk analysis

    B. Risk tolerance

    C. Risk management

    D. Risk attitude

  • Question 645:

    Which of the following buffers protects the target finish date from slippage along the critical chain?

    A. Critical buffer

    B. Project buffer

    C. Duration buffer

    D. Feeding buffer

  • Question 646:

    Which of the following are the components of the scope baseline?

    A. Project charter, project scope statement, and work breakdown structure (WBS)

    B. Project charter, project management plan, and plan procurement

    C. Project scope statement, work breakdown structure (WBS), and WBS dictionary

    D. Project management plan, plan procurement, and contract administration

  • Question 647:

    Which of the following are examples of interactive communication?

    A. Intranet sites

    B. Voice mails

    C. Video conferences

    D. Press releases

  • Question 648:

    Which of the following are documented directions to perform an activity that can reduce the probability of negative consequences associated with project risks?

    A. Recommended corrective actions

    B. Recommended preventive actions

    C. Risk audits

    D. Risk reassessments

  • Question 649:

    Which of following could be organizational process assets?

    A. Historical information

    B. Industry standards

    C. Organization infrastructure

    D. Marketplace conditions

  • Question 650:

    Which is the document that presents a hierarchical project organization?

    A. WBS

    B. CPI

    C. OBS

    D. BOM

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.