  • Question 631:

    Which of the following is an input to the Plan Risk Responses process?

    A. Risk urgency assessment

    B. Organizational process assets

    C. Risk register

    D. Schedule management plan

  • Question 632:

    Which of the following is an input into the Develop Project Team process?

    A. Enterprise environmental factors

    B. Organizational process assets

    C. Project staff assignments

    D. Performance reports

  • Question 633:

    Which of the following is an example of contract administration?

    A. Negotiating the contract

    B. Authorizing contractor work

    C. Developing the statement of work

    D. Establishing evaluation criteria

  • Question 634:

    Which of the following is an example of push communication?

    A. Intranet sites

    B. Video conferencing

    C. Knowledge repositories

    D. Press releases

  • Question 635:

    Which of the following is an example of a technique used in quantitative risk analysis?

    A. Sensitivity analysis

    B. Probability and impact matrix

    C. Risk data quality assessment

    D. Risk categorization

  • Question 636:

    Which of the following is an example of a risk symptom?

    A. Failure to meet intermediate milestones

    B. Force of nature, such as a flood

    C. Risk threshold target

    D. Crashing, front loading, or fast tracking

  • Question 637:

    Which of the following is a tool and technique used in all processes within Project Integration Management?

    A. Records management system

    B. Expert judgment

    C. Project management software

    D. Issue log

  • Question 638:

    Which of the following is a schematic display of the project's schedule activities and the logical relationships among them?

    A. Gantt chart

    B. Project schedule network diagram

    C. Project milestone list

    D. Activity list

  • Question 639:

    Which of the following is a schedule network analysis technique that takes limited resources into account?

    A. Network reserve analysis

    B. Critical chain method

    C. Lead and lag adjustment

    D. Critical path method

  • Question 640:

    Which of the following is a component of three-point estimates?

    A. Probabilistic

    B. Most likely

    C. Expected

    D. Anticipated

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.