What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A. Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination
What type of reward can hurt team cohesiveness?
A. Sole-sum
B. Win-lose
C. Lose-win
D. Partial-sum
Which of the following consists of the detailed project scope statement and its associated WBS and WBS dictionary?
A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline
What is the name of a graphic display of project team members and their reporting relationships?
A. Role dependencies chart
B. Reporting flow diagram
C. Project organization chart
D. Project team structure diagram
Which tool is used to develop technical details within the project management plan?
A. Expert judgment
B. Project management methodology
C. Project management information system (PMIS)
D. Project selection methods
Assigned risk ratings are based upon:
A. Root cause analysis.
B. Risk probability and impact assessment.
C. Expert judgment.
D. Revised stakeholders' tolerances.
Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing this dual reporting relationship factor?
A. Functional manager
B. Project manager
C. Functional manager supported by the project manager
D. Project management office
Within project integration management, the statement of work (SOW) references which aspects of the project?
A. Strategic plan, business need, and product scope description
B. Contract, enterprise environmental factors, and organizational process assets
C. Business plan, project management plan, and project schedule
D. Product lifecycle, business objective, and management strategy
Who MUST know when a risk event occurs so that a response can be implemented?
A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department.
Who is responsible for reviewing change requests and approving or rejecting the change requests?
A. Change control board
B. Project manager
C. Project management office
D. Project sponsor
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.