Exam Details

  • Exam Code
    :PMI-100
  • Exam Name
    :Certified Associate in Project Management(CAPM)
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :1073 Q&As
  • Last Updated
    :May 13, 2025

PMI CAPM PMI-100 Questions & Answers

  • Question 591:

    Which of the following processes are part of the Project Integration Management Knowledge Area?

    A. Develop Project Management Plan, Collect Requirements, Create WBS

    B. Develop Project Management Plan, Control Scope, Develop Schedule

    C. Develop Project Charter, Define Scope, Estimate Costs

    D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase

  • Question 592:

    An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

    A. Customer request

    B. Market demand

    C. Technological advance

    D. Strategic opportunity

  • Question 593:

    A procurement management plan is a subsidiary of which other type of plan?

    A. Resource plan

    B. Project management plan

    C. Cost control plan

    D. Expected monetary value plan

  • Question 594:

    A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:

    A. To the project management plan.

    B. To the risk register.

    C. In the scope verification processes.

    D. And their impact to the project in terms of time, cost, and risk.

  • Question 595:

    Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

    A. Perform Qualitative Risk Analysis

    B. Perform Quantitative Risk Analysis

    C. Plan Risk Management

    D. Plan Risk Responses

  • Question 596:

    Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?

    A. The influence of the stakeholders increases, the cost of changes increases.

    B. The influence of the stakeholders decreases, the cost of changes increases.

    C. The influence of the stakeholders increases, the cost of changes decreases.

    D. The influence of the stakeholders decreases, the cost of changes decreases.

  • Question 597:

    Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

    A. Control Schedule

    B. Define Activities

    C. Develop Schedule

    D. Estimate Activity Resources

  • Question 598:

    Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

    A. Bottom-up

    B. Three-point

    C. Parametric

    D. Analogous

  • Question 599:

    Perform Quality Control is accomplished by:

    A. Identifying quality standards that are relevant to the project and determining how to satisfy them.

    B. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes.

    C. Ensuring that the entire project team has been adequately trained in quality assurance processes.

    D. Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards.

  • Question 600:

    Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

    A. Critical path method

    B. Variance analysis

    C. Schedule compression

    D. Schedule comparison bar charts

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.