PMI CAPM PMI-100 Questions & Answers

  • Question 521:

    The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

    A. Control Schedule.

    B. Quality Control.

    C. Perform Integrated Change Control.

    D. Develop Schedule.

  • Question 522:

    One of the tools and techniques of the Manage Project Team process is:

    A. organization charts.

    B. ground rules.

    C. organizational theory,

    D. conflict management.

  • Question 523:

    Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

    A. Project

    B. Functional

    C. Program

    D. Portfolio

  • Question 524:

    A method to manage stakeholder expectations in the scope statement is to clearly:

    A. state the guiding principles of the organization.

    B. identify alternatives to generate different approaches.

    C. state what is out of scope.

    D. outline the results of the Delphi technique.

  • Question 525:

    Analogous cost estimating relies on which of the following techniques?

    A. Expert judgment

    B. Project management software

    C. Vendor bid analysis

    D. Reserve analysis

  • Question 526:

    Labor, materials, equipment, and supplies are examples of:

    A. Resource attributes.

    B. Resource types.

    C. Resource categories.

    D. Resource breakdown structures (RBS).

  • Question 527:

    Which technique helps to determine the risks that have the most potential impact on a project?

    A. Cost risk simulation analysis

    B. Expected monetary value analysis

    C. Modeling and simulation

    D. Sensitivity analysis

  • Question 528:

    Which of the following is an example of the simplest fixed-price contract?

    A. Purchase requisition

    B. Purchase order

    C. Verbal agreement

    D. Request for quote

  • Question 529:

    Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

    A. Plan Risk Responses

    B. Manage Stakeholder Expectations

    C. Define Scope

    D. Report Performance

  • Question 530:

    Which process involves identifying and documenting the logical relationships between project activities?

    A. Develop Schedule

    B. Sequence Activities

    C. Create WBS

    D. Applying leads and lags

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.