  • Question 541:

    Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

    A. Perform Quality Control

    B. Quality Metrics

    C. Perform Quality Assurance

    D. Plan Quality

  • Question 542:

    Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

    A. WBS directory

    B. Activity list

    C. WBS

    D. Project schedule

  • Question 543:

    Which process occurs within the Monitoring and Controlling Process Group?

    A. Control Costs

    B. Plan Quality

    C. Perform Quantitative Risk Analysis

    D. Determine Budget

  • Question 544:

    What risk technique is used to quantify the probability and impact of risks on project objectives?

    A. Expert judgment

    B. Risk registry

    C. Risk response planning

    D. Interviewing

  • Question 545:

    A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

    A. Cost-reimbursable

    B. Time and material

    C. Fixed price or lump-sum

    D. Cost-plus-fixed-fee

  • Question 546:

    In which process might a project manager use risk reassessment as a tool and technique?

    A. Perform Qualitative Risk Analysis

    B. Monitor and Control Risk

    C. Monitor and Control Project Work

    D. Plan Risk Responses

  • Question 547:

    In which domain of project management would a Pareto chart provide useful information?

    A. Project Scope Management

    B. Project Time Management

    C. Project Communications Management

    D. Project Quality Management

  • Question 548:

    Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

    A. Conduct Procurements.

    B. Close Procurements.

    C. Administer Procurements,

    D. Plan Procurements.

  • Question 549:

    Which of the following factors is lowest at the start of the project?

    A. Cost of changes

    B. Stakeholder influences

    C. Risk

    D. Uncertainty

  • Question 550:

    Which process determines the risks that might affect the project?

    A. Perform Qualitative Risk Analysis

    B. Identify Risks

    C. Plan Risk Management

    D. Perform Quantitative Risk Analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.