  • Question 501:

    Documented identification of a flaw in a project component together with a recommendation is termed a:

    A. corrective action.

    B. preventive action.

    C. non-conformance report,

    D. defect repair.

  • Question 502:

    Which of the following is an information gathering technique in Identify Risks?

    A. Influence diagrams

    B. Brainstorming

    C. Assumption analysis

    D. SWOT analysis

  • Question 503:

    Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

    A. Portfolio

    B. Process

    C. Project

    D. Program

  • Question 504:

    Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

    A. Limited

    B. Low to moderate

    C. Moderate to high

    D. High to almost total

  • Question 505:

    Which of the following is a tool or technique of the Define Activities process?

    A. Rolling wave planning

    B. Precedence diagramming method (PDM)

    C. Alternatives analysis

    D. Parametric estimating

  • Question 506:

    When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

    A. training, testing, and warranty work.

    B. equipment, rework, and scrap.

    C. training, document processes, and inspections.

    D. inspections, rework, and warranty work.

  • Question 507:

    Which process should be conducted from the project inception through completion?

    A. Monitor and Control Project Work

    B. Perform Quality Control

    C. Perform Integrated Change Control

    D. Monitor and Control Risks

  • Question 508:

    Which piece of information is part of the WBS Dictionary?

    A. Responsible organization

    B. Change requests

    C. Validated deliverables

    D. Organizational process assets

  • Question 509:

    The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?

    A. Resource leveling and fast tracking

    B. Fast tracking and crashing

    C. Crashing and applying leads and lags

    D. Scheduling tools and applying leads and lags

  • Question 510:

    Which of the following characteristics are found in a functional organizational structure?

    A. Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

    B. Limited project manager authority, limited resource availability, and a part-time project manager's role

    C. Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

    D. High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.