  • Question 441:

    Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

    A. -8000

    B. -2000

    C. 2000

    D. 8000

  • Question 442:

    Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?

    A. Cause and effect diagram

    B. Control charts

    C. Pareto chart

    D. Histogram

  • Question 443:

    What is a tool to improve team performance?

    A. Staffing plan

    B. External feedback

    C. Performance reports

    D. Co-location

  • Question 444:

    What is the primary benefit of meeting quality requirements?

    A. Quality metrics

    B. Less rework

    C. Quality control measurements

    D. Benchmarking

  • Question 445:

    The PV is $1000, EV is $2000, and AC is $1500. What is CPI?

    A. 1.33

    B. 2

    C. 0.75

    D. 0.5

  • Question 446:

    A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?

    A. Three weeks

    B. Four weeks

    C. Five weeks

    D. Six weeks

  • Question 447:

    During which process would stakeholders provide formal acceptance of the completed project scope?

    A. Perform Quality Control

    B. Verify Scope

    C. Control Scope

    D. Develop Schedule

  • Question 448:

    Co-location is a tool and technique of:

    A. Develop Human Resource Plan.

    B. Manage Project Team.

    C. Develop Project Team.

    D. Acquire Project Team.

  • Question 449:

    Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

    A. Perform Quality Control

    B. Perform Quality Assurance

    C. Plan Quality

    D. Report Performance

  • Question 450:

    Which of the following types of a dependency determination is used to define the sequence of activities?

    A. Legal

    B. Discretionary

    C. Internal

    D. Resource

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.