  • Question 341:

    Whose approval may be required for change requests after change control board (CCB) approval?

    A. Functional managers

    B. Business partners

    C. Customers or sponsors

    D. Subject matter experts

  • Question 342:

    The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

    A. adaptive

    B. reflexive

    C. predictive

    D. iterative

  • Question 343:

    Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

    A. project documents updates.

    B. project management plan updates.

    C. change requests.

    D. work performance information.

  • Question 344:

    Every project creates a unique product, service, or result that may be:

    A. tangible

    B. targeted

    C. organized

    D. variable

  • Question 345:

    The following is a network diagram for a project.

    The free float for Activity H is how many days?

    A. 4

    B. 5

    C. 10

    D. 11

  • Question 346:

    The following is a network diagram for a project.

    How many possible paths are identified for this project?

    A. 3

    B. 4

    C. 6

    D. 7

  • Question 347:

    Which element does a project charter contain?

    A. Management reserves

    B. Work breakdown structure

    C. Stakeholder list

    D. Stakeholder register

  • Question 348:

    The following is a network diagram for a project.

    What is the critical path for the project?

    A. A-B-C-F-G-I

    B. A-B-C-F-H-I

    C. A-D-E-F-G-I

    D. A-D-E-F-H-I

  • Question 349:

    Stakeholder communication requirements should be included as a component of:

    A. enterprise environmental factors

    B. organizational process assets

    C. the project management plan

    D. the stakeholder register

  • Question 350:

    In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

    A. Technical approach

    B. Technical capability

    C. Business size and type

    D. Production capacity and interest

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.