  • Question 331:

    Funding limit reconciliation is a tool and technique of which Project Cost Management process?

    A. Estimate Costs

    B. Control Costs

    C. Plan Cost Management D. Determine Budget

  • Question 332:

    Which Process Group includes the Manage Stakeholder Engagement process?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Initiating

  • Question 333:

    Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

    A. Business case

    B. Work breakdown structure

    C. Requirements documentation

    D. Risk register

  • Question 334:

    The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

    A. Close Procurements.

    B. Control Procurements.

    C. Plan Procurements.

    D. Conduct Procurements.

  • Question 335:

    Analytical techniques are a tool and technique of which process in Project Procurement Management?

    A. Plan Procurement Management

    B. Control Procurements

    C. Conduct Procurements

    D. Close Procurements

  • Question 336:

    Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

    A. Control chart

    B. Flowchart

    C. Checksheet

    D. Pareto diagram

  • Question 337:

    An intentional activity to modify a nonconforming product or product component is called:

    A. defect repair

    B. work repair

    C. corrective action

    D. preventive action

  • Question 338:

    Variance and trend analysis is a tool and technique used in which process?

    A. Perform Qualitative Risk Analysis

    B. Perform Quantitative Risk Analysis

    C. Control Risks

    D. Plan Risk Responses

  • Question 339:

    Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

    A. Influence/impact grid

    B. Power/influence grid

    C. Power/interest grid

    D. Salience model

  • Question 340:

    The primary benefit of the Plan Schedule Management process is that it:

    A. provides guidance to identify time or schedule challenges within the project.

    B. tightly links processes to create a seamless project schedule.

    C. guides how the project schedule will be managed throughout the project.

    D. creates an overview of all activities broken down into manageable subsections.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.