PMI CAPM PMI-100 Questions & Answers

  • Question 131:

    Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

    A. Nominal group technique

    B. Idea/mind mapping

    C. Affinity diagram

    D. Brainstorming

  • Question 132:

    A reward can only be effective if it is:

    A. Given immediately after the project is completed.

    B. Something that is tangible.

    C. Formally given during project performance appraisals.

    D. Satisfying a need valued by the individual.

  • Question 133:

    When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

    A. Negative

    B. Zero

    C. Positive

    D. Free

  • Question 134:

    The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

    A. Timing

    B. Methodology

    C. Risk categories

    D. Budgeting

  • Question 135:

    Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

    A. Expert judgment.

    B. Analytical techniques.

    C. Earned value management.

    D. Group decision-making techniques.

  • Question 136:

    Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

    A. Enhance

    B. Share

    C. Exploit

    D. Accept

  • Question 137:

    Which process in Project Time Management includes reserve analysis as a tool or technique?

    A. Estimate Activity Resources

    B. Sequence Activities

    C. Estimate Activity Durations

    D. Develop Schedule

  • Question 138:

    A project manager should document the escalation path for unresolved project risks in the:

    A. Change control plan

    B. Stakeholder register

    C. Risk log

    D. Communications management plan

  • Question 139:

    An output of the Plan Quality Management process is:

    A. A process improvement plan.

    B. Quality control measurements.

    C. Work performance information.

    D. The project management plan.

  • Question 140:

    An example of a group decision-ma king technique is:

    A. Nominal group technique.

    B. Majority.

    C. Affinity diagram.

    D. Multi-criteria decision analysis.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-100 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.