PMI PMI Certification PMI-001 Questions & Answers

  • Question 731:

    Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

    A. 100

    B. 120

    C. 1,000

    D. 1,200

  • Question 732:

    Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

    A. Uniform

    B. Continuous

    C. Discrete

    D. Linear

  • Question 733:

    Which document in the project management plan can be updated in the Plan Procurement Management process?

    A. Budget estimates

    B. Risk matrix

    C. Requirements documentation

    D. Procurement documents

  • Question 734:

    Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

    A. Estimate Costs

    B. Control Costs

    C. Plan Cost Management

    D. Determine Budget

  • Question 735:

    In project management, a temporary project can be:

    A. Completed without planning

    B. A routine business process

    C. Long in duration

    D. Ongoing to produce goods

  • Question 736:

    Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

    A. Collaboration

    B. Negotiation

    C. Decision making

    D. Influencing

  • Question 737:

    Which item is a cost of conformance?

    A. Training

    B. Liabilities

    C. Lost business

    D. Scrap

  • Question 738:

    Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

    A. Continuous

    B. Discrete

    C. Regulated

    D. Arbitrary

  • Question 739:

    A graphic display of project team members and their reporting relationships is known as a:

    A. Resource calendar.

    B. Project organization chart.

    C. Resource breakdown structure (RBS).

    D. Responsibility assignment matrix (RAM).

  • Question 740:

    The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

    A. recognition and rewards

    B. compliance

    C. staff acquisition

    D. training needs

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.