  • Question 741:

    The following is a network diagram for a project.

    The critical path for the project is how many days in duration?

    A. 10

    B. 12

    C. 14

    D. 17

  • Question 742:

    Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

    A. Influencing

    B. Motivation

    C. Negotiation

    D. Trust building

  • Question 743:

    The following is a network diagram for a project.

    The shortest non-critical path for the project is how many days in duration?

    A. 10

    B. 12

    C. 14

    D. 16

  • Question 744:

    Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

    A. Procurement documents

    B. Inspection and audits

    C. Estimate budget

    D. Risk register

  • Question 745:

    An example of a group decision-making technique is:

    A. nominal group technique

    B. majority

    C. affinity diagram

    D. multi-criteria decision analysis

  • Question 746:

    Which type of graphic is displayed below?

    A. Work breakdown structure

    B. Context diagram

    C. Control chart

    D. Pareto diagram

  • Question 747:

    The zero duration of milestones in project planning occurs because milestones:

    A. Are unpredictable and challenge the Plan Schedule Management process.

    B. Occur at random times in the project plans.

    C. Represent a moment in time such as a significant project point or event.

    D. Represent both significant and insignificant points in the project and are difficult to anticipate.

  • Question 748:

    When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

    A. improvement

    B. program

    C. result

    D. portfolio

  • Question 749:

    The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

    A. management

    B. response

    C. tolerance

    D. appetite

  • Question 750:

    Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

    A. organizational skills

    B. technical skills

    C. communication skills

    D. hard skills

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.