  • Question 721:

    The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

    A. exploit

    B. avoid

    C. mitigate

    D. share

  • Question 722:

    A complete set of concepts, terms, and activities that make up an area of specialization is known as:

    A. a Knowledge Area

    B. a Process Group

    C. program management

    D. portfolio management

  • Question 723:

    What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

    A. 0.03

    B. 0.06

    C. 0.10

    D. 0.50

  • Question 724:

    Which action is included in the Control Costs process?

    A. Identify how the project costs will be planned, structured, and controlled

    B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs

    C. Develop an approximation of the monetary resources needed to complete project activities

    D. Monitor cost performance to isolate and understand variances from the approved cost baseline

  • Question 725:

    When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

    A. lead

    B. lag

    C. mandatory dependency

    D. internal dependency

  • Question 726:

    Perform Integrated Change Control is the process of:

    A. Reviewing, approving, and managing all change requests

    B. Facilitating change management, manuals, or automation tools

    C. Comparing actual results with planned results in order to expand or change a project

    D. Documenting changes according to the change control system by the change control board

  • Question 727:

    Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

    A. Available organizational assets

    B. Project staff assignments

    C. Interpersonal skills

    D. Enterprise environmental factors

  • Question 728:

    Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

    A. Collect Requirements

    B. Plan Scope Management

    C. Define Scope

    D. Define Activities

  • Question 729:

    Which stakeholder approves a project's result?

    A. Customer

    B. Sponsor

    C. Seller

    D. Functional manager

  • Question 730:

    Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

    A. Update

    B. Preventive action

    C. Defect repair

    D. Corrective action

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.