Exam Details

  • Exam Code
    :PMI-001
  • Exam Name
    :Project Management Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :920 Q&As
  • Last Updated
    :May 08, 2025

PMI PMI Certification PMI-001 Questions & Answers

  • Question 681:

    Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

    A. Plan Cost Management

    B. Plan Scope Management

    C. Plan Stakeholder Management

    D. Plan Schedule Management

  • Question 682:

    A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an adverse effect on another deliverable. This could have been avoided if the project team had implemented:

    A. Quality assurance.

    B. A stakeholder management plan.

    C. Project team building.

    D. Integrated change control.

  • Question 683:

    Success is measured by benefits realization for a:

    A. strategic plan

    B. project

    C. portfolio

    D. program

  • Question 684:

    At the start of a typical project life cycle, costs are:

    A. low, peak as work is carried out, and drop as the project nears the end.

    B. low, become steady as work is carried out, and increase as the project nears the end.

    C. high, drop as work is carried out, and increase as the project nears the end.

    D. high, become low as work is carried out, and drop as the project nears the end.

  • Question 685:

    The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

    A. Acquire Project Team.

    B. Plan Human Resource Management.

    C. Manage Project Team.

    D. Develop Project Team.

  • Question 686:

    The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

    A. Estimate Costs

    B. Control Costs

    C. Plan Cost Management

    D. Determine Budget

  • Question 687:

    Which term describes an assessment of correctness?

    A. Accuracy

    B. Precision

    C. Grade

    D. Quality

  • Question 688:

    Project managers who lead by example and follow through on the commitments they make demonstrate the key interpersonal skill of:

    A. influencing

    B. leadership

    C. motivation

    D. coaching

  • Question 689:

    Which items are an output of the Perform Integrated Change Control process?

    A. Work performance reports

    B. Accepted deliverables

    C. Project management plan updates

    D. Organizational process assets

  • Question 690:

    A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:

    A. cultural differences of team members

    B. possibility of communication misunderstandings

    C. costs associated with travel

    D. costs associated with technology

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.