Those who enter into a contractual agreement to provide services necessary for a project are:
A. buyers
B. sellers
C. business partners
D. product users
In the Define Activities process, the schedule management plan is used to:
A. Capture the lessons learned from other projects for comparison.
B. Contain the standard activity list.
C. Document and support the project change requests.
D. Prescribe the level of detail needed to manage the work.
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
A. risk management plan
B. human resource management plan
C. scope management plan
D. procurement management plan
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
A. Schedule network analysis
B. Reserve analysis
C. Alternative analysis
D. Variance analysis
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
A. Decomposition
B. Inspection
C. Project analysis
D. Document analysis
One of the key benefits of the Plan Human Resource Management process is that it:
A. outlines team selection guidelines and team member responsibilities.
B. establishes project roles and responsibilities.
C. improves teamwork, interpersonal skills, and competencies.
D. provides an accurate appraisal of team member performance.
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
A. 0.83
B. 0.9
C. 1.11
D. 1.33
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost variance (CV) for Task 6?
A. -2,000
B. 0
C. 1,000
D. 2,000
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
A. -2,000
B. -1,000
C. 1,000
D. 2,000
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.