  • Question 651:

    An intentional activity to modify a nonconforming product or product component is called:

    A. defect repair

    B. work repair

    C. corrective action

    D. preventive action

  • Question 652:

    Variance and trend analysis is a tool and technique used in which process?

    A. Perform Qualitative Risk Analysis

    B. Perform Quantitative Risk Analysis

    C. Control Risks

    D. Plan Risk Responses

  • Question 653:

    The primary benefit of the Plan Schedule Management process is that it:

    A. provides guidance to identify time or schedule challenges within the project.

    B. tightly links processes to create a seamless project schedule.

    C. guides how the project schedule will be managed throughout the project.

    D. creates an overview of all activities broken down into manageable subsections.

  • Question 654:

    Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

    A. Influence/impact grid

    B. Power/influence grid

    C. Power/interest grid

    D. Salience model

  • Question 655:

    Whose approval may be required for change requests after change control board (CCB) approval?

    A. Functional managers

    B. Business partners

    C. Customers or sponsors

    D. Subject matter experts

  • Question 656:

    Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

    A. project documents updates.

    B. project management plan updates.

    C. change requests.

    D. work performance information.

  • Question 657:

    The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

    A. adaptive

    B. reflexive

    C. predictive

    D. iterative

  • Question 658:

    The following is a network diagram for a project.

    The free float for Activity H is how many days?

    A. 4

    B. 5

    C. 10

    D. 11

  • Question 659:

    Every project creates a unique product, service, or result that may be:

    A. tangible

    B. targeted

    C. organized

    D. variable

  • Question 660:

    The following is a network diagram for a project.

    How many possible paths are identified for this project?

    A. 3

    B. 4

    C. 6

    D. 7

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.