  • Question 641:

    The following is a network diagram for a project.

    What is the critical path for the project?

    A. A-B-D-G

    B. A-B-E-G

    C. A-C-F-G

    D. A-C-E-G

  • Question 642:

    The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

    A. appetite

    B. tolerance

    C. threshold

    D. management

  • Question 643:

    A project manager requesting industry groups and consultants to recommend project intervention is relying on:

    A. Communication models.

    B. Stakeholder participation.

    C. Expert judgment

    D. Enterprise environmental factors.

  • Question 644:

    Funding limit reconciliation is a tool and technique of which Project Cost Management process?

    A. Estimate Costs

    B. Control Costs

    C. Plan Cost Management

    D. Determine Budget

  • Question 645:

    In complex projects/ initiating processes should be completed:

    A. Within a work package.

    B. In each phase of the project.

    C. To estimate schedule constraints.

    D. To estimate resource allocations.

  • Question 646:

    Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

    A. Business case

    B. Work breakdown structure

    C. Requirements documentation

    D. Risk register

  • Question 647:

    Which Process Group includes the Manage Stakeholder Engagement process?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Initiating

  • Question 648:

    Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

    A. Control chart

    B. Flowchart

    C. Checksheet

    D. Pareto diagram

  • Question 649:

    Analytical techniques are a tool and technique of which process in Project Procurement Management?

    A. Plan Procurement Management

    B. Control Procurements

    C. Conduct Procurements

    D. Close Procurements

  • Question 650:

    The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

    A. Close Procurements.

    B. Control Procurements.

    C. Plan Procurements.

    D. Conduct Procurements.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.