  • Question 631:

    Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

    A. portfolio

    B. program

    C. selection

    D. sub portfolio

  • Question 632:

    The scope management plan and scope baseline are contained in:

    A. organizational process assets

    B. a requirements traceability matrix

    C. the project charter

    D. the project management plan

  • Question 633:

    High-level project risks are included in which document?

    A. Business case

    B. Risk breakdown structure

    C. Project charter

    D. Risk register

  • Question 634:

    Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?

    A. Cause-and-effect diagram

    B. Histogram

    C. Control chart

    D. Scatter diagram

  • Question 635:

    The component of the risk management plan that documents how risk activities will be recorded is called:

    A. tracking

    B. scoping

    C. timing

    D. defining

  • Question 636:

    Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

    A. Information management systems

    B. Work performance reports

    C. Stakeholder analysis

    D. Data gathering and representation

  • Question 637:

    The following is a network diagram for a project.

    The total float for the project is how many days?

    A. 3

    B. 5

    C. 7

    D. 9

  • Question 638:

    Tools and techniques used in Direct and Manage Project Work include:

    A. Process analysis and expert judgment

    B. Analytical techniques and a project management information system

    C. Performance reviews and meetings

    D. Expert judgment and meetings

  • Question 639:

    Completion of the product scope is measured against the product:

    A. prototypes

    B. requirements

    C. analyses

    D. benchmarks

  • Question 640:

    An issue log is an input to which Project Human Resource Management process?

    A. Manage Project Team

    B. Acquire Project Team

    C. Plan Human Resource Management

    D. Develop Project Team

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.