  • Question 561:

    Information collected on the status of project activities being performed to accomplish the project work is known as what?

    A. Project management information system

    B. Work performance information

    C. Work breakdown structure

    D. Variance analysis

  • Question 562:

    Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

    A. Project Integration Management

    B. Project Communications Management

    C. Project Information Management System (PIMS)

    D. Project Scope Management

  • Question 563:

    Which of the following tools or techniques is used for Estimate Activity Durations?

    A. Critical path method

    B. Rolling wave planning

    C. Precedence diagramming method

    D. Parametric estimating

  • Question 564:

    When would resource leveling be applied to a schedule model?

    A. Before constraints have been identified

    B. Before it has been analyzed by the critical path method

    C. After it has been analyzed by the critical path method

    D. After critical activities have been removed from the critical path

  • Question 565:

    Which of the following statements correctly characterizes pull communication?

    A. It includes letters, memos, reports, emails, and faxes.

    B. It requires recipients to access communication content at their own discretion.

    C. It is the most efficient way to ensure a common understanding among all participants.

    D. It is primarily used when the volume of information to be transferred is minimal.

  • Question 566:

    Which schedule network analysis technique modifies the project schedule to account for limited resources?

    A. Human resource planning

    B. Fast tracking

    C. Critical chain method

    D. Rolling wave planning

  • Question 567:

    Which of the following is an output of the Monitor and Control Project Work process?

    A. Change requests

    B. Performance reports

    C. Organizational process assets

    D. Project management plan

  • Question 568:

    Which of the following is a tool and technique for Estimate Activity Durations?

    A. Parametric estimating

    B. Monte Carlo analysis

    C. Alternatives analysis

    D. Bottom-up estimating

  • Question 569:

    Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

    A. Complete project phase

    B. Project life

    C. The project life cycle

    D. Project cycle

  • Question 570:

    Which of the following is contained within the communications management plan?

    A. An organizational chart

    B. Glossary of common terminology

    C. Organizational process assets

    D. Enterprise environmental factors

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.