  • Question 581:

    The product scope description is used to:

    A. Gain stakeholders' support for the project.

    B. Progressively elaborate the characteristics of the product, service, or result.

    C. Describe the project in great detail.

    D. Define the process and criteria for accepting a completed product, service, or result.

  • Question 582:

    Most experienced project managers know that:

    A. every project requires the use of all processes in the PMBOK?Guide.

    B. there is no single way to manage a project.

    C. project management techniques are risk free.

    D. there is only one way to manage projects successfully.

  • Question 583:

    Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

    A. Build vs. buy

    B. Expert judgment

    C. Alternatives identification

    D. Product analysis

  • Question 584:

    An output of Control Schedule is:

    A. A project schedule network diagram

    B. A schedule management plan

    C. Schedule data

    D. Schedule forecasts

  • Question 585:

    What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

    A. Failure modes and effects analysis

    B. Design of experiments

    C. Quality checklist

    D. Risk analysis

  • Question 586:

    The process of formalizing acceptance of the completed project deliverables is known as:

    A. Validate Scope.

    B. Close Project or Phase.

    C. Control Quality.

    D. Verify Scope.

  • Question 587:

    The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

    A. Push

    B. Pull

    C. Interactive

    D. Iterative

  • Question 588:

    Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

    A. Resource breakdown structure

    B. Staffing management plan

    C. Project organizational chart

    D. Scope management plan

  • Question 589:

    The scope of a project cannot be defined without some basic understanding of how to create the specified:

    A. objectives

    B. schedule

    C. product

    D. approach

  • Question 590:

    The procurement process that documents agreements and related documentation for future reference is known as:

    A. Plan Procurements.

    B. Control Procurements.

    C. Close Procurements.

    D. Conduct Procurements.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.