  • Question 551:

    Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?

    A. Organizational standard processes

    B. Marketplace conditions

    C. Historical information

    D. Templates

  • Question 552:

    During which process group is the quality policy determined?

    A. Initiating

    B. Executing

    C. Planning

    D. Controlling

  • Question 553:

    Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

    A. Analogous

    B. Parametric

    C. Bottom-up

    D. Top-down

  • Question 554:

    Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?

    A. Histogram

    B. Quality audits

    C. Benchmarking

    D. Performance measurement analysis

  • Question 555:

    Taking out insurance in relation to risk management is called what?

    A. Transference

    B. Avoidance

    C. Exploring

    D. Mitigation

  • Question 556:

    Which of the following investigates the likelihood that each specific risk will occur?

    A. Risk register

    B. Risk audits

    C. Risk urgency assessment

    D. Risk probability and impact assessment

  • Question 557:

    What is a hierarchically organized depiction of the identified project risks arranged by risk category?

    A. Risk register

    B. Risk breakdown structure (RBS)

    C. Risk management plan

    D. Risk category

  • Question 558:

    Which activity is an input to the Conduct Procurements process?

    A. Organizational process assets

    B. Resource availability

    C. Perform Integrated Change Control

    D. Team performance assessment

  • Question 559:

    What is the number of stakeholders, if the project has 28 potential communication channels?

    A. 7

    B. 8

    C. 14

    D. 16

  • Question 560:

    Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?

    A. Mitigate

    B. Transfer

    C. Share

    D. Avoid

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.