PMI PMI Certifications PMI-001 Questions & Answers

  • Question 541:

    Which is an example of Administer Procurements?

    A. Negotiating the contract

    B. Authorizing contractor work

    C. Developing the statement of work

    D. Establishing evaluation criteria

  • Question 542:

    An input to the Create WBS process is a: A. project charter.

    B. stakeholder register.

    C. project scope statement.

    D. requirements traceability matrix.

  • Question 543:

    The scope management plan is a subsidiary of which project document?

    A. Schedule management plan

    B. Project management plan

    C. Quality management plan

    D. Resource management plan

  • Question 544:

    Which enterprise environmental factors are considered during Estimate Costs?

    A. Market conditions and published commercial information

    B. Company structure and market conditions

    C. Commercial information and company structure

    D. Existing human resources and market conditions

  • Question 545:

    Who selects the appropriate processes for a project?

    A. Project stakeholders

    B. Project sponsor and project stakeholder

    C. Project manager and project team

    D. Project manager and project sponsor

  • Question 546:

    Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?

    A. The customer and functional managers

    B. The risk owners and stakeholders

    C. The sponsors and stakeholders

    D. The project management team

  • Question 547:

    In an organization with a projectized organizational structure, who controls the project budget?

    A. Functional manager

    B. Project manager

    C. Program manager

    D. Project management office

  • Question 548:

    Organizations perceive risks as:

    A. events that will inevitably impact project and organizational objectives.

    B. the effect of uncertainty on their project and organizational objectives.

    C. events which could have a negative impact on project and organizational objectives.

    D. the negative impact of undesired events on their project and organizational objectives.

  • Question 549:

    The Define Scope process is in which of the following Process Groups?

    A. Initiating

    B. Planning

    C. Monitoring and Controlling

    D. Executing

  • Question 550:

    What is the difference between the critical path and the critical chain?

    A. Scope changes

    B. Resource limitations

    C. Risk analysis

    D. Quality audits

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.