Projects are separated into phases or subprojects; these phases include:
A. feasibility study, concept development, design, and prototype.
B. initiate, plan, execute, and monitor.
C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.
D. Identify Stakeholders, develop concept, build, and test.
Resource calendars are included in the:
A. staffing management plan.
B. work breakdown structure (WBS).
C. project communications plan.
D. project charter.
Expected monetary value (EMV) is computed by which equation?
A. Value of each possible outcome multiplied by probability of occurrence
B. Value of each possible outcome multiplied by probability of non-occurrence
C. Multiplying the value of each possible outcome by the probability of occurrence and adding the products together
D. Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together
The process of identifying specific actions to be performed to produce project deliverables is:
A. Define Activities.
B. Create WBS.
C. Define Scope.
D. Develop Schedule.
What is project management?
A. A logical grouping of project management inputs, outputs, tools, and techniques
B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements
C. Launching a process that can result in the authorization of a new project
D. A formal, approved document that defines how the project is executed, monitored, and controlled
At the end of the project, what will be the value of SV?
A. Positive
B. Zero
C. Negative
D. Greater than one
Which is one of the determining factors used to calculate CPI?
A. EV
B. SPI
C. PV
D. ETC
Which process requires implementation of approved changes?
A. Direct and Manage Project Execution
B. Monitor and Control Project Work
C. Perform Integrated Change Control
D. Close Project or Phase
Which quality control technique illustrates the 80/20 principle?
A. Ishikawa diagram
B. Control chart
C. Run chart
D. Pareto chart
Which technique is utilized in the Control Schedule process?
A. Performance measure
B. Baseline schedule
C. Schedule network analysis
D. Variance analysis
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.