  • Question 301:

    Projects are separated into phases or subprojects; these phases include:

    A. feasibility study, concept development, design, and prototype.

    B. initiate, plan, execute, and monitor.

    C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance.

    D. Identify Stakeholders, develop concept, build, and test.

  • Question 302:

    Resource calendars are included in the:

    A. staffing management plan.

    B. work breakdown structure (WBS).

    C. project communications plan.

    D. project charter.

  • Question 303:

    Expected monetary value (EMV) is computed by which equation?

    A. Value of each possible outcome multiplied by probability of occurrence

    B. Value of each possible outcome multiplied by probability of non-occurrence

    C. Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

    D. Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

  • Question 304:

    The process of identifying specific actions to be performed to produce project deliverables is:

    A. Define Activities.

    B. Create WBS.

    C. Define Scope.

    D. Develop Schedule.

  • Question 305:

    What is project management?

    A. A logical grouping of project management inputs, outputs, tools, and techniques

    B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

    C. Launching a process that can result in the authorization of a new project

    D. A formal, approved document that defines how the project is executed, monitored, and controlled

  • Question 306:

    At the end of the project, what will be the value of SV?

    A. Positive

    B. Zero

    C. Negative

    D. Greater than one

  • Question 307:

    Which is one of the determining factors used to calculate CPI?

    A. EV

    B. SPI

    C. PV

    D. ETC

  • Question 308:

    Which process requires implementation of approved changes?

    A. Direct and Manage Project Execution

    B. Monitor and Control Project Work

    C. Perform Integrated Change Control

    D. Close Project or Phase

  • Question 309:

    Which quality control technique illustrates the 80/20 principle?

    A. Ishikawa diagram

    B. Control chart

    C. Run chart

    D. Pareto chart

  • Question 310:

    Which technique is utilized in the Control Schedule process?

    A. Performance measure

    B. Baseline schedule

    C. Schedule network analysis

    D. Variance analysis

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.