Which statement correctly describes the value of a business case?
A. It provides the necessary information to determine if a project is worth the required investment.
B. It provides for alternative dispute resolution procedures in event of contract default.
C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.
D. It is used to help a project manager understand the scope of commercial advantages.
Which of the following is a group decision-making technique?
A. Brainstorming
B. Focus groups
C. Affinity diagram
D. Plurality
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
A. Acquisition
B. Negotiation
C. Virtual team
D. Pre-assignment
While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?
A. Communications management plan
B. Human resource plan
C. Quality management plan
D. Procurement management plan
A tool and technique used during the Collect Requirements process is:
A. prototypes.
B. expert judgment.
C. alternatives identification.
D. product analysis.
One of the objectives of a quality audit is to:
A. highlight the need for root cause analysis.
B. share the process documentation among stakeholders.
C. offer assistance with non-value-added activities.
D. identify all of the gaps or shortcomings.
The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called: A. a control chart.
B. baseline.
C. Create WBS.
D. decomposition.
Which baselines make up the performance measurement baseline?
A. Scope baseline, cost baseline, and schedule baseline
B. Scope baseline, project management baseline, and quality baseline
C. Cost baseline, schedule baseline, and risk baseline
D. Cost baseline, project management baseline, and schedule baseline
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements describes management of which of the following?
A. Project
B. Scope
C. Contract
D. Program
Prototype development may be used as a tool for which of the following risk response strategies?
A. Avoid
B. Accept
C. Mitigate
D. Exploit
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.