  • Question 241:

    Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

    A. Estimate at completion

    B. Cost performance

    C. Schedule performance

    D. To-complete performance

  • Question 242:

    Which of the following is an output of the Conduct Procurements process?

    A. Project statement of work

    B. Selected sellers

    C. Risk register updates

    D. Teaming agreements

  • Question 243:

    The three processes of Project Cost Management are:

    A. Estimate Costs, Control Schedule, and Control Costs.

    B. Estimate Costs, Determine Budget, and Estimate Activity Resources.

    C. Determine Budget, Control Schedule, and Estimate Activity Resources.

    D. Estimate Costs, Determine Budget, and Control Costs.

  • Question 244:

    Which risk response strategy is common for both positive and negative risks?

    A. Share

    B. Accept

    C. Mitigate

    D. Transfer

  • Question 245:

    Risk responses reflect an organization's perceived balance between:

    A. risk taking and risk avoidance.

    B. known risk and unknown risk.

    C. identified risk and analyzed risk.

    D. varying degrees of risk.

  • Question 246:

    The correct equation for schedule variance (SV) is earned value:

    A. minus planned value [EV - PV].

    B. minus actual cost [EV - AC].

    C. divided by planned value [EV/PV],

    D. divided by actual cost [EV/AC].

  • Question 247:

    After Define Activities and Sequence Activities, the next process is:

    A. Estimate Activity Resources.

    B. Estimate Activity Durations,

    C. Develop Schedule.

    D. Control Schedule.

  • Question 248:

    Inputs to the Plan Risk Management process include the:

    A. cost management plan.

    B. risk management plan,

    C. activity list,

    D. risk register.

  • Question 249:

    Which of the following is an output of Define Scope?

    A. Project scope statement

    B. Project charter

    C. Project plan

    D. Project schedule

  • Question 250:

    Exhibit A is an example of which of the following types of Sequence Activities?

    A. Activity-on-arrow diagramming

    B. Precedence diagramming

    C. Project schedule network diagramming

    D. Mathematical analysis diagramming

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.