  • Question 221:

    Which of the following can be used as an input for Define Scope?

    A. Product analysis

    B. Project charter

    C. Scope baseline

    D. Project scope statement

  • Question 222:

    A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:

    A. Manage Stakeholder Expectations.

    B. Monitor and Control Risks.

    C. Plan Risk Management.

    D. Report Performance.

  • Question 223:

    The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

    A. majority rule technique.

    B. nominal group technique.

    C. Delphi technique,

    D. idea/mind mapping technique.

  • Question 224:

    At which stage of team development do members begin to work together, adjust work habits, and trust each other?

    A. Forming

    B. Storming

    C. Norming

    D. Performing

  • Question 225:

    When cost variance is negative and schedule variance is positive, the project is:

    A. under budget and behind schedule.

    B. over budget and ahead of schedule.

    C. on schedule.

    D. complete; all planned values have been earned.

  • Question 226:

    Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

    A. Reserve analysis

    B. Three-point estimating

    C. Parametric estimating

    D. Analogous estimating

  • Question 227:

    The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

    A. quality.

    B. value.

    C. technical performance.

    D. status.

  • Question 228:

    Which type of dependency is contractually required or inherent in the nature of the work?

    A. External

    B. Lead

    C. Discretionary

    D. Mandatory

  • Question 229:

    The contract in which the seller is reimbursed for all allowable costs for performing the contract work and then receives a fee based upon achieving certain performance objectives is called a:

    A. Cost Plus Incentive Fee Contract (CPIF).

    B. Cost Plus Fixed Fee Contract (CPFF).

    C. Fixed Price Incentive Fee Contract (FPIF).

    D. Time and Material Contract (TandM).

  • Question 230:

    Which of the following includes how requirements activities will be planned, tracked, and reported?

    A. Configuration management plan

    B. Scope baseline

    C. Requirements management plan

    D. Schedule baseline

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.