  • Question 201:

    Soft logic is also known as what type of dependency?

    A. External

    B. Discretionary

    C. Mandatory

    D. Internal

  • Question 202:

    Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?

    A. Risk response planning

    B. Manage stakeholders

    C. Scope definition

    D. Performance reporting

  • Question 203:

    Which of the following buffers protects the target finish date from slippage along the critical chain?

    A. Critical buffer

    B. Project buffer

    C. Duration buffer

    D. Feeding buffer

  • Question 204:

    What is the minimum a project schedule must include?

    A. Variance analysis

    B. A planned start date and a planned finish date for each schedule activity

    C. A critical path diagram

    D. Critical chain analysis

  • Question 205:

    What quality control tool graphically represents how various elements of a system interrelate?

    A. Control chart

    B. Flowchart

    C. Run chart

    D. Pareto chart

  • Question 206:

    Using the following data, what is the Schedule Performance Index (SPI)?

    EV= $500 PV= $750 AC= $1000 BAC= $1200

    A. 0.67

    B. 1.5

    C. 0.75

    D. 0.5

  • Question 207:

    Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

    A. Project Risk Management

    B. Project Integration Management

    C. Project Communications Management

    D. Project Quality Management

  • Question 208:

    Which activity is an input to the select sellers process?

    A. Organizational process assets

    B. Resource availability

    C. Change control process

    D. Team performance assessment

  • Question 209:

    Which of the following methods is a project selection technique?

    A. Flowcharting

    B. Earned value

    C. Cost-benefit analysis

    D. Pareto analysis

  • Question 210:

    On what is project baseline development established?

    A. Approved product requirements

    B. Estimated project cost and schedule

    C. Actual project cost and schedule

    D. Revised project cost and schedule

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.