    Which of the following tools or techniques is used for Estimate Activity Duration?

    A. Critical path

    B. Rolling Wave

    C. PDM

    D. Para metric

  • Question 192:

    Which of the following is a complete set of indexed contract documentation, including the closed contract?

    A. Procurement package

    B. Negotiated settlements

    C. Procurement file

    D. Procurement management plan

  • Question 193:

    Which type of analysis is used to develop the communications management plan?

    A. Product

    B. Cost benefit

    C. Stakeholder

    D. Research

  • Question 194:

    What is an objective of the Developing Project Team Process?

    A. Feelings of trust and improved cohesiveness

    B. Ground rules for interaction

    C. Enhanced resource availability

    D. Functional managers become more involved.

  • Question 195:

    You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?

    A. Perform periodic project performance reviews.

    B. Identify quality project standards.

    C. Follow ISO 9000 quality standards.

    D. Complete the quality control checklist.

  • Question 196:

    Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

    A. Risk identification

    B. Qualitative risk analysis

    C. Risk management planning

    D. Quantitative risk analysis

  • Question 197:

    When does risk monitoring and control occur?

    A. At project initiation

    B. During work performance analysis

    C. Throughout the life of the project

    D. At project milestones

  • Question 198:

    Who MUST know when a risk event occurs so that a response can be implemented?

    A. Customers

    B. Project sponsors

    C. Project management team

    D. Insurance claims department

  • Question 199:

    What are the components of the "triple constraint"?

    A. Scope, time, requirements

    B. Resources, time, cost

    C. Scope, management, cost

    D. Scope, time, cost

  • Question 200:

    During what process is the quality policy determined?

    A. Initiating

    B. Executing

    C. Planning

    D. Controlling

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.