  • Question 181:

    Which of the following is the correct network diagram for the table?

    A. Begin-A-C-D-E-End-B-D

    B. Begin-A-B-C-D-E-End

    C. Begin-A-B-D-E-End A-C-D

    D. Begin-A-C-D-E-End-B-C

  • Question 182:

    Which of the following are inputs to Activity Definition?

    A. Project Scope Statement and Work Breakdown Structure

    B. Activity list and Arrow Diagram

    C. Change Requests Lists and Organizational Process Assets

    D. Project Management Plan and Resource Availability

  • Question 183:

    Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

    A. Qualitative risk analysis

    B. Quantitative risk analysis

    C. Risk management planning

    D. Risk response planning

  • Question 184:

    Which of the following lists contain processes that are included within Project Procurement Management?

    A. Plan purchases and acquisitions, plan contracting, request seller responses, select sellers

    B. Plan purchases and acquisitions, request seller responses, select sellers, schedule control

    C. Plan purchases and acquisitions, acquire project team, request seller responses, select sellers

    D. Plan purchases and acquisitions, acquire project team, contract approval, select sellers

  • Question 185:

    Which tools or techniques will the project manager use for developing the project team?

    A. Negotiation

    B. Roles and responsibilities

    C. Recognition and rewards

    D. Prizing and promoting

  • Question 186:

    A project manager's authority is limited within which of the following organizational structures?

    A. Functional

    B. Projectized

    C. Weak Matrix

    D. Balanced Matrix

  • Question 187:

    What defines the portion of work included in a contract for items being purchased or acquired?

    A. Procurement management plan

    B. Evaluation criteria

    C. Work Breakdown Structure (WBS)

    D. Contract Statement of Work (SOW)

  • Question 188:

    Which of the following is a tool and technique for activity duration estimating?

    A. Parametric estimating

    B. Monte Carlo analysis

    C. Top-down estimating

    D. Bottom-up estimating

  • Question 189:

    An in put required to develop a preliminary project scope statement is:

    A. Organizational Structure

    B. Organizational Process Assets

    C. Organizational Matrix

    D. Organizational Breakdown Structures

  • Question 190:

    Which of the following is an example of a risk symptom?

    A. Failure to meet intermediate milestones

    B. Force of nature, such as a flood

    C. Risk threshold target

    D. Crashing, front loading, or fast tracking

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.