  • Question 501:

    Which tool or technique measures performance of the project as it moves from project initiation through project closure?

    A. Resource leveling

    B. Parametric measuring

    C. Pareto chart

    D. Earned value

  • Question 502:

    Which of the following are outputs of the Monitor and Control Project Work process?

    A. Requested changes, forecasts, recommended corrective actions

    B. Forecasts, resources plan, bottom up estimating

    C. Recommended corrective actions, cost baseline, forecasts D. Requested changes, recommended corrective actions, project constraints

  • Question 503:

    Which tool is used to develop technical details within the project management plan?

    A. Expert Judgment

    B. Project Management Methodology

    C. Project Management Information

    D. Project Selection Methods

  • Question 504:

    While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

    A. Utilize the change control process.

    B. Crash the schedule to fix the defect.

    C. Leave the defect in and work around it.

    D. Fast-track the remaining development.

  • Question 505:

    Which of the following methods is a project selection technique?

    A. Flowcharting

    B. Earned value

    C. Cost-benefit analysis

    D. Pareto analysis

  • Question 506:

    Which activity is an input to the select sellers process?

    A. Organizational process assets

    B. Resource availability

    C. Change control process

    D. Team performance assessment

  • Question 507:

    What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

    A. Pareto

    B. Ishikawa

    C. Shewart-Deming

    D. Delphi

  • Question 508:

    The Define Scope process is in which of the following process groups?

    A. Initiating

    B. Planning

    C. Monitoring and Controlling

    D. Executing

  • Question 509:

    Which of the following processes is necessary to ensure that the project employs all processes needed to meet its requirements?

    A. Perform Quality Control

    B. Quality Policy

    C. Perform Quality Assurance

    D. Quality Planning

  • Question 510:

    Which process occurs within the Monitoring and Controlling Process Group?

    A. Cost Control

    B. Quality Planning

    C. Quantitative Risk Analysis

    D. Cost Budgeting

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.