Exam Details

  • Exam Code
    :CA0-001
  • Exam Name
    :Certified Associate in Project Management
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :530 Q&As
  • Last Updated
    :May 02, 2025

PMI CAPM CA0-001 Questions & Answers

  • Question 481:

    Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?

    A. -$8,000

    B. -$2,000

    C. $2,000

    D. $8,000

  • Question 482:

    The PV is $1000, EV is $2000 and AC is $1500. What is CPI?

    A. 1.33

    B. 2.00

    C. 0.75

    D. 0.5

  • Question 483:

    At the end of the project, what will be the value of SV?

    A. Positive

    B. Zero

    C. Negative

    D. Greater than one

  • Question 484:

    Cost baseline is an output of which of the following processes?

    A. Cost Control

    B. Cost Budgeting

    C. Cost Estimating

    D. Cost Planning

  • Question 485:

    Analogous Cost Estimating relies on which of the following techniques?

    A. Expert Judgment

    B. Project Management Software

    C. Vendor Bid Analysis

    D. Reserve Analysis

  • Question 486:

    The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:

    Actual cost = $50,000 Plan cost = $45,000 Earned value = $40,000 What is the cost performance index?

    A. 0.80

    B. 0.89

    C. 1.13

    D. 1.25

  • Question 487:

    Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

    A. Performance organizations

    B. Schedule baselines

    C. Performance measurements

    D. Change requests

  • Question 488:

    Which technique is utilized in the Schedule Control process?

    A. Performance Measure

    B. Baseline Schedule

    C. Schedule Comparison

    D. Variance Analysis

  • Question 489:

    Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

    A. Applying calendars

    B. Resource Leveling

    C. Resource Planning

    D. Resource Conflict Management

  • Question 490:

    Project scope statement and resource calendars are inputs to what Project Time Management process?

    A. Activity Sequencing

    B. Activity Resource Estimating

    C. Schedule Development

    D. Schedule Control

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.