  • Question 181:

    The product description of a project can help to create procurement details. Which one of the following best describes product description?

    A. The product description defines the contracted work, based on the requirements of the project customer

    B. The product description defines the contracted work

    C. The product description defines the requirements for the contract work

    D. Al1 of the above

  • Question 182:

    Based on the PMBOK, who is ultimately responsible for the project quality?

    A. Project team

    B. Project manager

    C. QA manager

    D. Validation engineer

  • Question 183:

    The end of the project comes after which of the following?

    A. Project charter

    B. F'na' deliverable

    C. Schedule

    D. QA activities are done

  • Question 184:

    Most change requests are a result of .

    A. Value added change (enhancements)

    B. Schedule constraints

    C. Regulatory constraints

    D. Improvement to the project scope

  • Question 185:

    Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of .

    A. Enterprise benefits measurement methods when selecting a project

    B. Integral parts of the SOW

    C. Ways to ensure stakeholder commitment

    D. Project selection methods

  • Question 186:

    A Risk Register is a part of the .

    A. Project Scope Statement

    B. Project Management plan

    C. Project Scheduling plan

    D. Project Charter

  • Question 187:

    Create Procurement document is done in .

    A. Plan Procurements

    B. Conduct Procurements

    C. Administer Procurements

    D. Close Procurements

  • Question 188:

    Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?

    A. Precedence Diagramming Method (PDM)

    B. Gant Cnart Diagram (GCD)

    C. Dependency Diagramming Method (DDM)

    D. Arrow Diagramming Method (ADM)

  • Question 189:

    A Risk Register is a part of the .

    A. Project Scope Statement

    B. Project Management plan

    C. Project Scheduling plan

    D. Project Charter

  • Question 190:

    In PMBOK, the seller is to the project team.

    A. Internal

    B. External

    C. Outside

    D. Assigned

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.