EXIN EXIN Agile Scrum Foundation ASF Questions & Answers

  • Question 21:

    In a Daily Scrum, one of the Team members complains about frequent interruptions by non-Team members.

    Which person should remove this impediment?

    A. The Product Owner

    B. The Scrum Master

    C. The Development Team

  • Question 22:

    All Scrum events are time-boxed events. What is the advantage of time-boxing?

    A. It ensures commitment of the Team.

    B. It facilitates osmotic communication.

    C. It maximizes productivity.

  • Question 23:

    You want to convince a customer of the benefits of Scrum. What is the key benefit of Scrum for the customer?

    A. Scrum ensures that the customer receives value early in the project.

    B. Scrum will give customers more control over day-to-day activities.

    C. Scrum will help the Team accept changes into the project at no additional cost.

  • Question 24:

    The team determines that it has over-committed itself for a Sprint. Who should be present when reviewing and adjusting the Sprint work?

    A. The team, the Scrum Master and the Product Owner. The Stakeholders should be consulted.

    B. The team and the Scrum Master. The Product Owner should be consulted.

    C. The team only. The Product Owner should be consulted.

  • Question 25:

    Why are estimates expressed in terms of story points difficult to explain outside of the team?

    A. It requires a comparison to a benchmark, which typically varies from team to team.

    B. It requires a deeper understanding of the technical approach to implement each story.

    C. It requires breaking the stories down into Sprint Backlog Items, which only the team can do.

  • Question 26:

    One of the Scrum Team members has the job to make sure that the customer gets the most value from the project.

    How do we call this role?

    A. The Product Owner

    B. The Scrum Master

    C. The Development Team

  • Question 27:

    Suppose that you track the Sprint progress in a Burn-Down chart. You have added an extra line to show the planned progress. The line of the actual progress stays below the planning line.

    What does this say about the progress?

    A. You are ahead of schedule.

    B. You are behind schedule.

    C. You have not planned well.

  • Question 28:

    Who is accountable for a task that is assigned to a single Team member?

    A. The Product Owner

    B. The Scrum Master

    C. The Development Team

    D. The single Team member

  • Question 29:

    Product Backlog Items must be non-technical and independent. Why should the Product Backlog Items be independent?

    A. Because it must be possible to organize the items according to value.

    B. Because there are themes that create a capability in the solution.

    C. Because not more than 10% of the time is spent grooming the items.

  • Question 30:

    Who is responsible for implementing the actions agreed upon by the team during a Retrospective?

    A. The Product Owner

    B. The Scrum Master

    C. The team

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ASF exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.