EXIN EXIN Agile Scrum Foundation ASF Questions & Answers

  • Question 41:

    Which is a statement of value as described in the Agile manifesto?

    A. We value customer collaboration over responding to changes.

    B. We value project management over individuals and interactions.

    C. We value processes and tools over comprehensive documentation.

    D. We value responding to change to satisfy the customer.

  • Question 42:

    A team decided to install a large traffic light in the team hall to indicate whether the latest build was healthy

    (green), failing a few tests (orange) or failing high priority tests (red).

    What term can be used to describe the traffic light?

    A. Information radiator

    B. Osmotic communication

    C. Triangulation

  • Question 43:

    Why is planning poker an effective estimation technique?

    A. It generates a lot of useful discussion and gets team buy-in.

    B. It results in lower estimates as team members will estimate individually.

    C. It triggers a more detailed and task oriented break-up of the story.

  • Question 44:

    What is a Scrum-of-Scrums?

    A. A meeting for management to get insight into the working of teams.

    B. A meeting for Scrum Masters of international Scrum teams.

    C. A meeting to coordinate the work of multiple Scrum teams.

    D. A meeting to show the customer an update of the product.

  • Question 45:

    Why does the Daily Scrum need to be held at the same location and time?

    A. The booking of a room needs to be done in advance for the duration of the Sprint.

    B. The constant time and place is best for continuity of the Scrum framework.

    C. The Project Manager needs to get the status updates at a given time every day.

  • Question 46:

    A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points.

    Which statement is true regarding this scenario?

    A. Points are assigned by the Scrum Master, not by the team.

    B. Points are assigned for the overall Story, not for parts of the Story.

    C. Points are never estimated, but always determined beforehand.

    D. The team forgets to ask the Product Owner about the estimate.

  • Question 47:

    For a Sprint, progress is monitored in a burn-up chart with bars. What makes the bar become longer?

    A. The progression of time.

    B. Work is added to the Sprint Backlog.

    C. Work is deleted from the Sprint Backlog.

  • Question 48:

    A 200 member project team is working on a large and complex system with multiple sub-systems. They would like to start using the Agile Scrum methodology.

    As a Scrum Master, what would your best advice be?

    A. Scrum is not suited for such a large project. The team should clearly use the Waterfall method or the Crystal Clear method.

    B. Ask all potential members of the project team to have a meeting first and decide if they agree to use Scrum.

    C. Agree a logical sub-division of the system so that smaller Scrum teams can work on sub-systems and can add tangible value.

  • Question 49:

    A team has eleven members spread over two locations across two time zones. One of the locations has six team members and the other team has five.

    Where should a Scrum Master be located?

    A. Alternate the Scrum Master between both locations.

    B. Appoint a local Scrum Master for both teams.

    C. The Scrum Master is located in one of the teams.

  • Question 50:

    A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.

    What is the elapsed time required to complete the story?

    A. 1.25 days

    B. 1.33 days

    C. 2 days

    D. This cannot be determined without knowing the velocity.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ASF exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.