EXIN EXIN Agile Scrum Foundation ASF Questions & Answers

  • Question 71:

    How does Agile bring predictability to the Planning process?

    A. By allowing the customers to review the progress often.

    B. By assigning most of the responsibility to the Product Owner.

    C. By making the team self-organized and self-planning.

    D. By providing early visibility into the team's progress.

  • Question 72:

    Which statement describes Release Planning?

    A. After looking at all the stories in the backlog, the team estimates their effort in detail.

    B. The team meets with the customer to negotiate the scope, cost and time of the release.

    C. The team and the Product Owner agree on an initial plan for the delivery of features.

  • Question 73:

    Agile planning happens at multiple levels including a daily plan,a sprint plan and a strategic plan. What term best describes the multi-level planning?

    A. Planning Onion

    B. Planning Poker

    C. Sprint Planning

  • Question 74:

    During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.

    What is the velocity of the team?

    A. 18

    B. 24.5

    C. 31

  • Question 75:

    What is the objective of the Scrum-of-Scrums meeting?

    A. To inform management about the progress of the project.

    B. Bring together all team members of all teams.

    C. Coordinate the work of multiple Scrum teams.

    D. Kick-off an international Scrum project.

  • Question 76:

    Under what circumstances would a team use Affinity Estimation Technique instead of Planning Poker?

    A. If more details are needed during Sprint Planning

    B. If there is a large number of stories to estimate

    C. If there is a small number of stories to estimate

  • Question 77:

    In a Scrum project, when would a requirement get added to the Product backlog?

    A. When it is developed, but cannot yet be released.

    B. When the team works on it for a particular release.

    C. When the customer requests a new requirement.

  • Question 78:

    Who should update the work estimates during the Sprint?

    A. The Development Team

    B. The Project Manager

    C. The Product Owner

  • Question 79:

    Which means of communication is the most preferable to clarify the interpretation of a requirement?

    A. E-mail

    B. Face-to-face

    C. Instant messaging

    D. Telephone

  • Question 80:

    A customer requests a report that summarizes functionality added and defects found and fixed, right at the end of a Sprint.

    Who may best prepare this report?

    A. The Product Owner

    B. The Scrum Master

    C. The team

    D. This type of report should not be prepared.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ASF exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.