    Which of the following project documents is an input to the Control Scope process?

    A. Vendor risk assessment diagram

    B. Risk register

    C. Requirements traceability matrix

    D. Area of responsibility summary

  • Question 172:

    Which of the following is a tool and technique used in the Develop Schedule process?

    A. Three-point estimates

    B. Resource leveling

    C. Precedence diagramming method

    D. Bottom-up estimating

  • Question 173:

    The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

    A. stakeholder management strategy.

    B. communications management plan.

    C. stakeholder register.

    D. performance report.

  • Question 174:

    Which tool or technique is used in Manage Stakeholder Expectations?

    A. Stakeholder management strategy

    B. Communication methods

    C. Issue log

    D. Change requests

  • Question 175:

    Which of the following are outputs of Develop Project Team?

    A. Human resources plan changes and project staff assignment updates

    B. Project management plan updates and enterprise environmental factor updates

    C. Resource calendars and project management plan updates

    D. Team performance assessments and enterprise environmental factor updates

  • Question 176:

    The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

    A. Executing.

    B. Initiating.

    C. Monitoring and Controlling.

    D. Planning.

  • Question 177:

    How many Project Management Process Groups are there?

    A. 3

    B. 4

    C. 5

    D. 6

  • Question 178:

    Which type of estimating is used to improve the accuracy of an activity's duration?

    A. Analogous

    B. Parametric

    C. Three-point

    D. What-if scenario analysis

  • Question 179:

    The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

    A. Determine Budget.

    B. Baseline Budget.

    C. Control Costs.

    D. Estimate Costs.

  • Question 180:

    To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

    A. scope creep.

    B. a change request.

    C. work performance information.

    D. deliverables.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.