  • Question 161:

    When addressing roles and responsibilities, which item ensures that the staff has the skills required to complete project activities?

    A. Authority

    B. Role

    C. Competency

    D. Responsibility

  • Question 162:

    Which of the following reduces the probability of potential consequences of project risk events?

    A. Preventive action

    B. Risk management

    C. Corrective action

    D. Defect repair

  • Question 163:

    Monte Carlo is which type of risk analysis technique?

    A. Probability

    B. Quantitative

    C. Qualitative

    D. Sensitivity

  • Question 164:

    Which is the correct formula for calculating expected activity cost for three-point estimating?

    A. Ce = (C0 + 6Cm + Cp)/4

    B. Ce = (6C0 + Cm + Cp)/4

    C. Ce = (C0 + 4Cm + Cp)/6

    D. Ce = (C0 + C,,, + 4Cp) / 6

  • Question 165:

    Which can be used to determine whether a process is stable or has predictable performance?

    A. Matrix diagram

    B. Histogram

    C. Control chart

    D. Flowchart

  • Question 166:

    When sequencing activities, what does the common acronym FF stand for?

    A. Fixed Fee

    B. Free Float

    C. Fixed Finish

    D. Finish-to-Finish

  • Question 167:

    Which is used to solicit proposals from prospective sellers?

    A. Procurement statement of work

    B. Resource calendars

    C. Procurement document

    D. Independent estimates

  • Question 168:

    In which Project Management Process Group is the project charter developed?

    A. Monitoring and Controlling

    B. Executing

    C. Initiating

    D. Planning

  • Question 169:

    What is the responsibility of the project manager and the functional manager respectively?

    A. Oversight for an administrative area; a facet of the core business

    B. Achieving the project objectives; providing management oversight for an administrative area

    C. A facet of the core business; achieving the project objectives

    D. Both are responsible for achieving the project objectives.

  • Question 170:

    The progressive detailing of the project management plan is called:

    A. expert judgment.

    B. rolling wave planning.

    C. work performance information.

    D. specification.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.