GAQM GAQM Certifications APM-001 Questions & Answers

  • Question 181:

    The definition of operations is a/an:

    A. organizational function performing the temporary execution of activities that produce the same product or provide repetitive service.

    B. temporary endeavor undertaken to create a unique product, service, or result.

    C. organization that provides oversight for an administrative area.

    D. organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service.

  • Question 182:

    Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?

    A. Teaming

    B. Collective bargaining

    C. Sharing

    D. Working

  • Question 183:

    Which Process Group contains those processes performed to define a new project?

    A. Initiating

    B. Planning

    C. Executing

    D. Closing

  • Question 184:

    The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?

    A. Transfer

    B. Share

    C. Avoid

    D. Accept

  • Question 185:

    The precedence diagramming method (PDM) is also known as:

    A. Arrow Diagram.

    B. Critical Path Methodology (CPM).

    C. Activity-On-Node (AON).

    D. schedule network diagram.

  • Question 186:

    Change request status updates are an output of which process?

    A. Perform Integrated Change Control

    B. Direct and Manage Project Execution

    C. Close Project or Phase

    D. Monitor and Control Project Work

  • Question 187:

    As the project progresses, which of the following is routinely collected from the project activities?

    A. Communication management activities

    B. Change requests

    C. Configuration verification and audit

    D. Work performance information

  • Question 188:

    Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

    A. Compromising

    B. Collaborating

    C. Smoothing

    D. Problem Solving

  • Question 189:

    A tool or technique in Perform Quality Control that a project manager would use is:

    A. quality audits.

    B. process analysis.

    C. benchmarking.

    D. inspection.

  • Question 190:

    In Project Cost Management, which input is exclusive to the Determine Budget process?

    A. Scope baseline

    B. Organizational process assets

    C. Project schedule

    D. Resource calendars

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.