Oracle 1Z0-567 Online Questions & Answers

  • Question 61:

    The Open Requests for Resource's portlet lists unstaffed assignments involving roles on the selected role team. Identify two ways that the portlet display can be organized.

    A. Role by Project
    B. Role by Resource
    C. Project by Role
    D. Resource by Project
    E. Resource by Role

  • Question 62:

    Identify the true statement regarding currency preferences for viewing currency.

    A. They are globally set and controlled by administrators.
    B. They are managed by an interface to a financial system (FMS).
    C. They are set by individuals in user preferences.
    D. They are permanently set during installation.

  • Question 63:

    Select the statement that best describes "Manage Scenarios" functionality.

    A. You can create a portfolio for your own use or for sharing.
    B. You can view portfolio data in different forms.
    C. You can capture a snapshot of project data.
    D. You can select a portfolio to work with or execute commands.

  • Question 64:

    Identify the best definition of the EPS.

    A. The hierarchical definition of project budgets and actual costs.
    B. The hierarchical definition of reporting structures.
    C. The hierarchical structure of the security for projects.
    D. The hierarchical structure of the database of projects.

  • Question 65:

    Where are workflows accessed?

    A. In portfolios
    B. In the EPS
    C. In the dashboards
    D. In the workspace

  • Question 66:

    You are an implementation consultant working at a company where project schedules have been managed primarily with Microsoft Project, on individual desktops.

    The "projects" theoretically have been multiple-year projects. Your scope of work includes migrating project data from legacy project plans and setting up project planning standards. As you look into the current Microsoft Project plans, it

    becomes clear that the projects are not really multi-year projects. The plans have been managed by creating "new" projects within the old projects by skipping a few lines in what has become more of a program history.

    What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a "one project, one plan" process?

    A. Import all MS Project plans directly into the P6 production database "as is."
    B. Import MS Project plans but break out current in-flight work into separate projects.
    C. Create new projects only for in flight work identified in MS Project plans.
    D. Retire legacy project plans and start with new project planning standards.

  • Question 67:

    Identity the true statement regarding the Must Finish By constraint.

    A. The Must Finish By constraint is used as the starting date for the backward pass.
    B. The Must Finish By constraint forces all activities in the project to finish by that date.
    C. The Must Finish By constraint affects the total Role limits for the project.
    D. All activities have negative total float when a Must Finish By constraint is assigned.

  • Question 68:

    Identify this icon:

    A. Customize Columns in the View
    B. Customize Tabs in the Details
    C. Customize GANTT Chart Options
    D. Customize and Save View

  • Question 69:

    You are a program manager reviewing portfolio performance data. You see that many issues are assigned to a "responsible manager." What does "responsible manager" mean with Primavera P6 EPPM?

    A. The person responsible for resolving the issue
    B. The person who identified the issue
    C. The element from the OBS associated with the issue
    D. the manager to which the issue has been assigned

  • Question 70:

    You are in a governance organization that has established a project management methodology with work product and document requirements that must be included in every project. You are doing an audit prior to a gate review for a specific project. You are fairly certain that the project manager and project are in compliance with these requirements, but you cannot see the required work products and documents in the project workspace.

    How can you solve this problem?

    A. Go to Activities and search tor the Work Products and Documents by using an Activity view.
    B. Go to a dashboard and look for the Work Products and Documents in a portlet.
    C. Create a global activity code for required Work Products and Documents to call out activities.
    D. Go to the Project section and click Work Products and Documents to view the portlet.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-567 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.