Oracle 1Z0-567 Online Questions & Answers

  • Question 11:

    Your customer wants to take advantage of capacity planning in portfolios. The customer would like to use generic resources, because they have greater flexibility to respond to changing costs by resource by location. In fact, they would prefer not to set up any roles at all in the database, because they perceive generic resources and roles to be duplicate effort.

    What would an appropriate response be to this customer?

    A. Use generic resources in Capacity Planning view, because they have greater ability to respond to changing costs.
    B. User generic resources for project financials, and mirrored roles for capacity planning.
    C. Use roles for planning and project financials to eliminate duplicate data maintenance.
    D. Integrate with HR systems to obtain automated generic resource pricing updates.

  • Question 12:

    You are developing a reporting strategy for a customer who requires monthly reports showing cost variance. The customer has two requirements.

    1.

    Each report must come from Primavera.

    2.

    Each month's report must become a "snapshot" for legal traceability purposes. Which P6 R8 solution addresses each of the customer's requirements?

    A. Email monthly report to distribution list
    B. Send reports directly to printers at all user locations
    C. Archive printed reports in files under security
    D. Send generated report to content repository

  • Question 13:

    What is the process that must be followed by a system administrator to create a user?

    A. Create an email account to confirm access after user setup.
    B. Assign a global profile, project profile, and responsible manager.
    C. Request approval from the user's manager before completing the profile.
    D. Assign a role to the user before assigning security profiles.

  • Question 14:

    Select the true statement regarding live or summarized data.

    A. Live data is used for resource management.
    B. Live data is used for portfolio management.
    C. Summarized data is used for resource management.
    D. Summarized data is used for project management.

  • Question 15:

    In your project, cost and work effort is not subject to change. Which duration type should be used?

    A. Fixed Units
    B. Fixed Duration and Units/Time
    C. Fixed Units/Time
    D. Fixed Duration and Units

  • Question 16:

    Identify the true statement regarding Schedule Checker.

    A. Before running Schedule Checker, you should schedule the project.
    B. Schedule Checker evaluates the WBS structure to demonstrate standards compliance.
    C. Schedule Checker is run from the Portfolios section.
    D. Run Schedule Checker before scheduling the project to fix issues.

  • Question 17:

    You are an application administrator. You received a change request to alter the relationship between an EPS node and its associated OBS element.

    What would be a prudent course of action to complete before moving forward with this change?

    A. Merge the old OBS element with the requested OBS element.
    B. Create a new OBS element per the change request.
    C. Determine which users would be affected.
    D. Delete the old OBS element per change request.

  • Question 18:

    By default, a role's limit is determined by_____________.

    A. the manually entered value on the Limit tab in the Role Dictionary
    B. the combined limit of all resources assigned to the role
    C. the combined limit of all primary resources assigned to the role
    D. the combined limit of all primary resources assigned to a project

  • Question 19:

    An activity is to be completed within a fixed time period and the total effort is also fixed. What duration type should be used?

    A. Fixed Units
    B. Fixed Duration and Units/Time
    C. Fixed Units/Time
    D. Fixed Duration and Units

  • Question 20:

    You are a portfolio manager. You opened a portfolio and you refreshed the filter. However, some of the projects that were previously in the portfolio are no longer there.

    What happened?

    A. You no longer have sufficient project-level security to view the "missing" project's data.
    B. Your web interface license was revoked to allow other users to interface with the projects.
    C. The value of the code assigned to the missing projects has changed.
    D. The projects were deleted when the filter was refreshed.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-567 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.