  • Question 21:

    Consider the following scenario:

    1) Receipt Days Early = 5; Receipt Days Late = 10; Receipt Days Exceed-Action = Reject

    2) Over Receipt Tolerance (%) = 5; Over Receipt Action = Reject

    3) Receipt Close Point = Received; Receipt Close Percent = 5%

    A shipment of 100 for item A was scheduled to be delivered on Oct-15-2007. Which receipt transaction(s) can occur?

    A. A receipt of 95 for item A is created on Oct-09-2007.
    B. A receipt of 90 for item A is created on Oct-27-2007.
    C. A receipt of 108 for item A is created on Oct-16-2007.
    D. A receipt of 60 for item A is created on Oct-12-2007. Another receipt of 65 for itemA is created on Oct-17-2007.
    E. A receipt of 70 for item A is created on Oct-12-2007. Another receipt of 28 for itemA is created on Oct-17-2007.

  • Question 22:

    While defining Approval Groups, which three objects can you define authorization rules for? (Choose three.)

    A. Buyer
    B. Location
    C. Commodity
    D. Item Category
    E. Account Range
    F. Document Amount

  • Question 23:

    Company X is a global company with operations in three regions: North America, Europe, and Asia. Each region has a separate business group, and one legal entity attached to each business group. North America has two operating units (OU) and the other two regions (Europe and Asia) have one OU each. Identify two correct statements regarding purchasing document approval and routing processes. (Choose two.)

    A. All three regions must share the same approval hierarchy.
    B. North America can have two sets of Approval Groups, one for each OU.
    C. North America can have only one set of Approval Groups to share across each OU.
    D. Each region can have a different type of hierarchy: Employee/Supervisor or Position Hierarchy.
    E. Each region can have a different approval hierarchy, but all three regions must use the same type of hierarchy: Employee/Supervisor or Position Hierarchy.

  • Question 24:

    Which two options would you use to restrict the functionality provided by a responsibility? (Choose two.)

    A. creating an appropriate role
    B. creating an appropriate group
    C. constructing a new menu hierarchy
    D. defining rules to exclude specific functions

  • Question 25:

    When you view Item Supply and Demand Information on the Supply/Demand Detail form, Available Quantity is _________.

    A. the quantity on hand
    B. the nettable quantity on hand
    C. the reservable quantity on hand
    D. the projected on-hand quantity of the item, defined as: (all future sources of supply)
    E. the projected on-hand quantity of the item, defined as: (current available) + (all future sources of supply)

  • Question 26:

    You are moving items from locator A to locator B within the same inventory organization. Which two types of inventory transactions are required? (Choose two.)

    A. Move Order
    B. Locator transfer
    C. Subinventory transfer
    D. WIP component issue
    E. Miscellaneous Receipt
    F. WIP assembly completion
    G. Interorganization transfer direct

  • Question 27:

    Which three statements are true about modifying Flexfield values? (Choose three.)

    A. The values cannot be disabled.
    B. The value description can be changed.
    C. The effective dates for a value can be limited.
    D. The values can be deleted after they are defined.
    E. The values cannot be modified after they are defined.

  • Question 28:

    How many distinct ABC Compile Names can exist at a given time in an inventory organization?

    A. an unlimited number of names
    B. only one for each subinventory
    C. only one per inventory organization
    D. one for each subinventory and one for each inventory organization

  • Question 29:

    ABC Inc. is a semiconductor manufacturing organization. They have all possible inventory controls on items. Which controls are validated on subinventory transfer transactions?

    1.

    Lot control

    2.

    Locator control

    3.

    Serial Number control

    4.

    Revision Quantity control

    5.

    Subinventory and locator restrictions for specific items

    A. 1
    B. 1 and 3
    C. 1, 3, and 5
    D. 1, 2, and 3
    E. 1 through 5
    F. 1, 2, 3, and 5
    G. 1, 2, 3, and 4

  • Question 30:

    Your client uses Average Costing to value the items in the inventory. A Miscellaneous Receipt transaction has been submitted for a quantity of 1 of an item. What are the two possible values that could have been added to the Material Account by this transaction? (Choose two.)

    A. 1 x (User-entered Unit Cost)
    B. 1 x (Current Average Unit Cost)
    C. The transaction will not be costed until the next Cost Manager program is executed.
    D. 1 x (Average Cost Variance), calculated when the next Cost Manager program is executed

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-520 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.