Oracle 1Z0-466 Online Questions & Answers

  • Question 91:

    Select two objectives of the OUM Manage Project Execution and Control phase.

    A. Manage the project resources to deliver on time and in budget.
    B. Gain project acceptance.
    C. Release staff.
    D. Execute against the Project Management Plan.

  • Question 92:

    What is not true about risk management in OUM Manage?

    A. The project manager should regularly conduct risk assessments.
    B. Risks become even more critical during the Project Execution and Control Phase.
    C. Particular attention should be paid to risks prior to production cutover.
    D. If a baseline risk assessment is done during the Project Startup phase, there are no further risk assessment required on the project.

  • Question 93:

    According to the recommended training for this exam, proper management ensures and .

    A. Value to the client
    B. Value to your company
    C. Value to the industry
    D. Value to the community

  • Question 94:

    Select three types of Envision engagements.

    A. Establish an enterprise IT Governance process.
    B. Install and configure an application.
    C. Define a SOA enterprise engineering process.
    D. Design and build a custom application.
    E. Implement an Enterprise Repository.
    F. Integrate an off-the-shelf application with another application.

  • Question 95:

    Which two statements are true about planning in OUM?

    A. A work product is always included for every task in the project workplan.
    B. Unnecessary tasks can be eliminated from the project workplan.
    C. Each task in OUM needs to be included in the project workplan.
    D. Tasks can be combined depending on the scope and risk of the project.
    E. Tasks can be eliminated when there is no staff assigned to them.

  • Question 96:

    Which three risks does Organizational Change Management seek to mitigate?

    A. Employee attrition
    B. Vendor delivery rates
    C. Lack of personal effectiveness
    D. Interruptions to the business
    E. Natural disasters

  • Question 97:

    At the end of iteration phase, during Project Execution and Control, which three key tasks should be conducted?

    A. QM.050 Perform Quality Assurance
    B. WM.050 ManageApprovals
    C. CMM.030 Manage Project Team Communication
    D. PKM.020 Conduct Baseline Risk Assessment
    E. SM.060 Close Scope management
    F. PKM.060 Conduct Post-Production Risk Assessment
    G. OCHM.040 Establish Follow-Up process

  • Question 98:

    Select three benefits of using OUM manage.

    A. It encourages early stakeholder involvement.
    B. It is less costly.
    C. It emphasizes clearly documenting the scope of the project and the terms and procedures to implement change.
    D. It encourages use of third-party resources.
    E. It supports improved communication.
    F. It provides incentives to finish projects early.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-466 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.