Which three features are part of Oracle Fusion Functional Setup Manager?
A. feature opt-in for a best fit configurationWhich application generates external roles to grant both function and data security? ( Choose the best answer.)
A. Authorization Policy ManagerYou configure one OTBI using Project Cross Subject Area Analysis Real Time. You notice that all measures (Budget, Forecast, Cost, Commitments, Revenue, and Invoice) are not available for Bill-To-Customer and Contract and Contract Line dimensions. Identify the reason for this behavior. (Choose the best answer.)
A. The Bill-To-Customer dimension applies only to Invoice measures, but the Contract and Contract Line dimensions do not apply to Revenue and Invoice measures.Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?
A. Enterprise Contract ManagementYour customer wants a project start date to cascade to the project tasks but does not want the finish date to be cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best answer.)
A. Cascade change to the start date.Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)
A. Project Manager Template for Project Organization SecurityYour customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
A. Calendar TypesWhich three are true of what you can do in the Project Requirements work area?
A. Create an implementation project.Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1.
Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2.
Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)
A. After the creation of Sub Task 1, Project Start Date would remain unchanged as 01-Jul-2016 and Sub Task 2 would be created with 15-Jun-2016.Which component provides a human workflow service that handles all interactions with users or groups in business processes?
A. Security ConsoleNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-1057-23 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.