Question 21:
Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)
A. Calendar Types B. Project Accounting Periods C. Accounting Periods D. PA Calendar E. PA-GL Periods
B. Project Accounting Periods C. Accounting Periods
Reference:
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_87F467307D50416BE040D30A68816855 Spread curves let you distribute quantity, cost, and revenue amounts automatically across accounting or project accounting periods. You
assign a spread curve to each resource class. Planning resources (in the planning resource breakdown structure) inherit the spread curve setting from the associated resource class. You can change the spread curve for the planning
resource and for any corresponding task assignments, or budget or forecast lines.
Question 22:
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)
A. Allocate rental costs once each accounting period by using the "full" allocation method. B. Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period. C. Define allocation basis by using Actual Amounts with a project-to-date amount class. D. Define allocation basis by using Actual Amounts with a period-to-date amount class. E. Allocate rental costs once each accounting period by using the "spread evenly" allocation method.
A. Allocate rental costs once each accounting period by using the "full" allocation method. B. Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period. D. Define allocation basis by using Actual Amounts with a period-to-date amount class.
Question 23:
A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)
A. The employee is not assigned to the project-owning organization. B. The employee is not assigned with a supervisor. C. Project roles are not assigned in the project. D. The employee is not assigned to a department.
D. The employee is not assigned to a department.
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project- foundation-configuration-define-project-resource-breakdown-structures.html#OAPFM180158_2 Why can't I find persons in the list of resources
when I enter team members, planning resources, or person rate schedules?
You can't find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations:
The administrator didn't assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or
entered as resources on the planning resource breakdown structure or person rate schedule.
The resource isn't active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated
effective start dates option when you search for the person.
Persons assigned as project managers aren't active as of the project start date. The assignment of the person is terminated, and an appropriate value isn't set for the number of days to display people with terminated assignments. You can set
the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.
Question 24:
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task B. expenditure type exclusions on the Capitalized Interest rate name C. expenditure type exclusions on the Capitalized Interest rate schedules D. expenditure items whose cost spreads across multiple assets that are capitalized E. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure items whose costs are applied to a single asset or multiple assets
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)
A. Both the contract lines create only a single invoice because they are using the same contract. B. Two invoices are created using the same contract. C. Bill set number drives the grouping of transactions. D. Invoice generation does not depend on bill plan. The invoices are created based on the contract line.
B. Two invoices are created using the same contract. C. Bill set number drives the grouping of transactions.
Ref: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJB/F1087456AN1006D.htm What's a bill set? Transactions originating from different bill plans with the same bill set number on a contract are included on the same invoice. If a contract has multiple bill plans and each have different values for the bill set, Oracle Fusion Project Billing creates a separate invoice for each bill plan
Question 26:
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions"
ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)
A. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to NO, cost is transferred to projects by receipt accounting. B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables. C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines. D. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to project by payables.
B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables. C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines.
Question 27:
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
A. P B. Q C. R D. S
C. R
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapem/evaluate- and-assign-resources.html#OAPEM916359 Topic - Resource Available Capacity Score: How It's Calculated Calendars Used to Calculate Resource Available Capacity Scores How the Resource Available Capacity Score Is Calculated
Question 28:
When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track. Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
A. multiple threshold levels B. single threshold level value C. single threshold level range D. multiple threshold level value
B. single threshold level value
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjs/update- project-performance-data-and-generate-kpis.html#OAPJS16654 Performance Status Indicator Performance status indicators give an immediate picture of the status of a project, such as critical, at risk, and on track. Each distinct icon indicates the status and severity of performance. During KPI definition, you first associate status indicators with performance statuses: Critical Severe At risk On track Ahead You then associate these statuses with threshold levels. When KPI values are generated for a project, each value is compared to the defined thresholds and the corresponding status indicator for the KPI appears on project performance reports. A status can identify negative performance so that you can take the appropriate actions to prevent or quickly resolve problems. Conversely, a status can identify positive performance to help you track expected or excellent performance. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing- project-financial-management-applications.html#FAPFM975706 Create Key Performance Indicators Create key performance indicators (KPI) to measure how well your organization performs an operational, tactical, or strategic activity that is critical for the current and future success of the organization. Note: To create KPIs you must enable a project unit to track key performance indicators. Use the Threshold Levels section to specify thresholds to indicate the health status of a KPI. Select one of the following options: Multiple threshold levels Single threshold level value Single threshold level range
Question 29:
Which product offering enables non-exclusive relationships between multiple projects and tasks with contracts and contract lines? (Choose the best answer.)
A. Project Contract-based costing B. Project Contract-based billing C. Project Contract Collection Center D. Contract Team Connect
B. Project Contract-based billing
Reference: http://www.oracle.com/us/products/applications/fusion/fusion-proj-port-mang-solut- brief-173079.pdf (Page 2) Flexible Contract-Based Billing Traditional contract and billing systems enforce a rigid relationship between a project and a funding agreement, which can constrain project setup and execution. Oracle Fusion Project Portfolio Management provides a highly flexible approach to project contract-based billing via a non-exclusive relationship between multiple projects and tasks with contracts and contract lines. This means that you will have full control over defining contracts, rates and limits, and when and how to recognize revenue and generate invoices while segregating the planning and execution of your projects.
Question 30:
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based
on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Which three are parameters that are based on which the system identifies the new resources?
A. Department B. Project Unit C. Jobs D. Business Unit E. Organization
Nowadays, the certification exams become more and more important and required by more and more
enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare
for the exam in a short time with less efforts? How to get a ideal result and how to find the
most reliable resources? Here on Vcedump.com, you will find all the answers.
Vcedump.com provide not only Oracle exam questions,
answers and explanations but also complete assistance on your exam preparation and certification
application. If you are confused on your 1Z0-1057-22 exam preparations
and Oracle certification application, do not hesitate to visit our
Vcedump.com to find your solutions here.