Q35
Single choice
Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date.
Management has asked her the project's Estimate To Complete (ETC) based on the current project performance.
What is the ETC for this project?